Which three items must be updated when scope changes are approved?

The correct answer is A. Project scope B. Project budget E. Project schedule. Project scope is the part of project planning that involves determining and documenting a list of specific project goals, deliverables, tasks, costs and deadlines.

Project Execution and Control

Question

Which three items must be updated when scope changes are approved?

Options

  • AProject scope
  • BProject budget
  • CProject component value ratio
  • DProject cost center
  • EProject schedule

How the community answered

(43 responses)
  • A
    81% (35)
  • C
    5% (2)
  • D
    14% (6)

Explanation

Project scope is the part of project planning that involves determining and documenting a list of specific project goals, deliverables, tasks, costs and deadlines.

Topics

#scope change management#change control#project budget#project schedule