What is the most important aspect of closing the project?
The correct answer is D. Formal client acceptance is gained. Oracle 1Z0-466 Exam The Project Closure phase occurs after the Production phase. During this phase, the project is "closed" from an administrative and contractual standpoint. This includes making sure that the project work products are complete and meet the customer's…
Question
What is the most important aspect of closing the project?
Options
- ASuccessful go-live.
- BEnd-user training is complete.
- CProject Team finds new assignments.
- DFormal client acceptance is gained.
How the community answered
(65 responses)- A15% (10)
- B3% (2)
- C8% (5)
- D74% (48)
Explanation
Oracle 1Z0-466 Exam The Project Closure phase occurs after the Production phase. During this phase, the project is "closed" from an administrative and contractual standpoint. This includes making sure that the project work products are complete and meet the customer's expectations; gaining final acceptance (D); and securing all documents for reuse, collection and retention.