What describes the nature of the activities within the Project Execution and Control phase?
The correct answer is A. They are dependent upon one another. The Manage focus area has three phases: - Project Start Up Phase - Project Execution and Control Phase - Project Closure Phase Integration of the Manage focus area phases with the Implement focus area phases is illustrated Oracle 1Z0-466 Exam
Project Execution and Control
Question
What describes the nature of the activities within the Project Execution and Control phase?
Options
- AThey are dependent upon one another.
- BThey are dependent upon earned value.
- CThey are ongoing.
- DThey are grouped according to priority.
How the community answered
(49 responses)- A82% (40)
- B6% (3)
- C2% (1)
- D10% (5)
Explanation
The Manage focus area has three phases: - Project Start Up Phase - Project Execution and Control Phase - Project Closure Phase Integration of the Manage focus area phases with the Implement focus area phases is illustrated Oracle 1Z0-466 Exam
Topics
#project execution and control#ongoing activities#OUM phases#activity dependencies