1Z0-466 · Question #31

Which two items are completed during the Work Management close?

The correct answer is A. final backup and archiving of the project workplan C. production of final schedule metric report. Note: Work Management - The objective of the Work Management process is to develop the work plan and to define and document the processes and policies to be used to execute, maintain, control and close-out the Project Workplan.

Project Execution and Control

Question

Which two items are completed during the Work Management close?

Options

  • Afinal backup and archiving of the project workplan
  • Bback up of the project diary
  • Cproduction of final schedule metric report
  • Dpayment of all vendor invoices
  • Ereconciliation of open accounts payable

How the community answered

(55 responses)
  • A
    71% (39)
  • B
    9% (5)
  • D
    16% (9)
  • E
    4% (2)

Explanation

Note: Work Management - The objective of the Work Management process is to develop the work plan and to define and document the processes and policies to be used to execute, maintain, control and close-out the Project Workplan.

Topics

#work management close#project workplan archiving#schedule metric report#project closure