1Z0-466 · Question #65
In the OUM Manage Focus Area, which process is started and completed within a single phase?
The correct answer is A. Bid Transaction. A: Bid Transition The Bid Transition process, Typically represented in Project Start Up, is in reality more of a project initiation task. The first major activity that a project manager is expected to perform is to participate in the handoff from the "sales cycle" to the…
Question
In the OUM Manage Focus Area, which process is started and completed within a single phase?
Options
- ABid Transaction
- BScope management
- CRisk Management
- DProject Closure
How the community answered
(30 responses)- A80% (24)
- B3% (1)
- C10% (3)
- D7% (2)
Explanation
A: Bid Transition The Bid Transition process, Typically represented in Project Start Up, is in reality more of a project initiation task. The first major activity that a project manager is expected to perform is to participate in the handoff from the "sales cycle" to the "delivery cycle". Not B: Scope Management - The goal of the Scope Management process is to identify clear boundaries of what is to be implemented and what key work products are to be produced. Not C: Risk Management - Risk Management is a structured process for identifying, documenting, gaining agreement on, and communicating risks throughout the lifecycle of a project.