What is one of the first outputs of the Project Execution and Control Phase?
The correct answer is D. Go-live cutover. The purpose of the Project Execution and Control Phase is to provide adequate visibility into actual progress so that management can take effective actions when the project's performance deviates significantly from the project plans. The Project Execution and Control Phase…
Question
What is one of the first outputs of the Project Execution and Control Phase?
Options
- AStaff retention plan
- BTeam orientation and kickoff
- CProject sponsor orientation and kickoff
- DGo-live cutover
- EContract sign-off
How the community answered
(31 responses)- B6% (2)
- C10% (3)
- D81% (25)
- E3% (1)
Explanation
The purpose of the Project Execution and Control Phase is to provide adequate visibility into actual progress so that management can take effective actions when the project's performance deviates significantly from the project plans. The Project Execution and Control Phase includes tracking and reviewing the projects accomplishments and results against documented WBS, project estimates, time schedule, resources plan, and cost budget, and adjusting these plans based on the actual accomplishment and results.