In which process does the Review and Analyze Bid Materials drive the Validated Scope in the Scope Management process?

The correct answer is D. Bid Transition. Bid Transition The Bid Transition process, Typically represented in Project Start Up, is in reality more of a project initiation task. The first major activity that a project manager is expected to perform is to participate in the handoff from the "sales cycle" to the "delivery…

Planning and Scheduling

Question

In which process does the Review and Analyze Bid Materials drive the Validated Scope in the Scope Management process?

Options

  • AFinancial Management
  • BInfrastructure Management
  • COrganizational Change Management
  • DBid Transition

How the community answered

(16 responses)
  • A
    6% (1)
  • C
    13% (2)
  • D
    81% (13)

Explanation

  • Bid Transition The Bid Transition process, Typically represented in Project Start Up, is in reality more of a project initiation task. The first major activity that a project manager is expected to perform is to participate in the handoff from the "sales cycle" to the "delivery cycle". * The Manage focus area is organized into 13 processes: ,,h Bid Transition ,,h Scope Management ,,h Financial Management ,,h Work Management ,,h Risk Management ,,h Issue and Problem Management ,,h Staff Management ,,h Communication Management ,,h Quality Management ,,h Configuration Management ,,h Infrastructure Management ,,h Procurement Management ,,h Organizational Change Management Collectively, these processes form a comprehensive set of tasks required to manage Oracle- based development and implementation projects. Every project includes most, if not all, of these whether they are the responsibility of a consulting organization, a client organization, or a third

Topics

#scope management#bid transition#validated scope#project phases