1Z0-466 · Question #37
Which is the true about OUM Manage?
The correct answer is D. If the client is not interested in helping to produce the necessary plans, then at a minimum, they are. Oracle 1Z0-466 Exam
Planning and Scheduling
Question
Which is the true about OUM Manage?
Options
- AIf the client is not involved in the planning process, the project should move ahead without approval.
- BIf the client is involved in the planning process, the project should move ahead without approval.
- CThe plans are only produced by the project team.
- DIf the client is not interested in helping to produce the necessary plans, then at a minimum, they are
- EIf the client is not interested to produce necessary plans, the project manager must limit the scope of
How the community answered
(38 responses)- A3% (1)
- B5% (2)
- C11% (4)
- D79% (30)
- E3% (1)
Explanation
Oracle 1Z0-466 Exam
Topics
#OUM Manage#client involvement#project approval#planning process