1Z0-466 · Question #37

Which is the true about OUM Manage?

The correct answer is D. If the client is not interested in helping to produce the necessary plans, then at a minimum, they are. Oracle 1Z0-466 Exam

Planning and Scheduling

Question

Which is the true about OUM Manage?

Options

  • AIf the client is not involved in the planning process, the project should move ahead without approval.
  • BIf the client is involved in the planning process, the project should move ahead without approval.
  • CThe plans are only produced by the project team.
  • DIf the client is not interested in helping to produce the necessary plans, then at a minimum, they are
  • EIf the client is not interested to produce necessary plans, the project manager must limit the scope of

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    11% (4)
  • D
    79% (30)
  • E
    3% (1)

Explanation

Oracle 1Z0-466 Exam

Topics

#OUM Manage#client involvement#project approval#planning process