1Z0-466 · Question #56

What is true about the Implementation Plan?

The correct answer is D. It focuses on the objectives, milestones, and number of iterations for the project. In a project setting, the Implementation Plan is a high level plan that focuses on milestones, Oracle 1Z0-466 Exam objectives, and the number of iterations. It is the plan that is typically developed at the start of an engagement identifying the project phases and milestones.

Planning and Scheduling

Question

What is true about the Implementation Plan?

Options

  • AIt shows the detailed tasks for the duration of the project.
  • BIt is not modified after the Project Execution and Control phase begins.
  • CIt is a subset of the Project Management Plan.
  • DIt focuses on the objectives, milestones, and number of iterations for the project
  • EIt covers a single phase.

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    13% (4)
  • C
    3% (1)
  • D
    74% (23)
  • E
    3% (1)

Explanation

In a project setting, the Implementation Plan is a high level plan that focuses on milestones, Oracle 1Z0-466 Exam objectives, and the number of iterations. It is the plan that is typically developed at the start of an engagement identifying the project phases and milestones.

Topics

#Implementation Plan#milestones#iterations#OUM planning