1Z0-466 · Question #71

Which three statements are true about the Validated Scope of the project?

The correct answer is B. It documents the boundaries of the project. D. It documents the contents of the Work Breakdown Structure. E. It is a key input to the Project Management Plan.. B: Scope Management - The goal of the Scope Management process is to identify clear boundaries of what is to be implemented and what key work products are to be produced. D: A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into their suc

Planning and Scheduling

Question

Which three statements are true about the Validated Scope of the project?

Options

  • AIt uses outputs of the Bid Transition process as a prerequisite.
  • BIt documents the boundaries of the project.
  • CIt documents only contractual deliverables.
  • DIt documents the contents of the Work Breakdown Structure.
  • EIt is a key input to the Project Management Plan.

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    81% (17)
  • C
    10% (2)

Explanation

B: Scope Management - The goal of the Scope Management process is to identify clear boundaries of what is to be implemented and what key work products are to be produced. D: A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into their successively higher level "parent" tasks, materials, etc. For each element of the work breakdown structure, a description of the task to be performed is generated. This technique (sometimes called a system breakdown structure) is used to define and organize the total scope

Topics

#validated scope#Work Breakdown Structure#Project Management Plan#scope documentation