1Z0-466 · Question #69
What involvement is a critical success factor in reviewing the project scope and approach and determining the Project Management Framework?
The correct answer is F. Stakeholders. All people and organizations that have an interest in the project or its outcome are called project stakeholders. The stakeholders provide input to the requirements of the project and the direction the project should take throughout its life cycle. The list of stakeholders can…
Question
What involvement is a critical success factor in reviewing the project scope and approach and determining the Project Management Framework?
Options
- AClient
- BSales
- CDelivery
- DConsulting
- ESteering Committee
- FStakeholders
How the community answered
(27 responses)- A7% (2)
- B11% (3)
- C4% (1)
- D4% (1)
- F74% (20)
Explanation
All people and organizations that have an interest in the project or its outcome are called project stakeholders. The stakeholders provide input to the requirements of the project and the direction the project should take throughout its life cycle. The list of stakeholders can be large and can change as the project matures. One of the first requirements to properly manage a project is the creation of a key stakeholder list. Be very careful to include all key stakeholders. Many projects have been derailed due to the political fallout of excluding a key stakeholder. Every potential stakeholder cannot be included in all aspects of a project, so it is important to identify the stakeholders who represent all stakeholders.
Topics
Community Discussion
No community discussion yet for this question.