Which statement is true about the Custom Development Sub-Flow of the OUM Implement Core Workflow?
Sign in or unlock 1Z0-466 to reveal the answer and full explanation for question #39. The question stem and answer options stay visible for context.
Planning and Scheduling
Question
Which statement is true about the Custom Development Sub-Flow of the OUM Implement Core Workflow?
Options
- AIt should be included in every OUM project plan.
- BIt should be included in the workplan when there are configuration tasks identified.
- CIt should be included in the workplan when gaps are identified while mapping requirements.
- DIt should only be included on SOA projects.
Unlock 1Z0-466 to see the answer
You've previewed enough free 1Z0-466 questions. Unlock 1Z0-466 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#OUM Implement#Custom Development Sub-Flow#workplan inclusion#gap analysis