1Z0-466 · Question #61

Which three statements are true about the various plans used In OUM during Project Execution Control.

The correct answer is B. The subsequent Iteration Plan is created prior to the beginning of the next iteration. C. The Project Management Plan should be updated, as appropriate. E. The current Iteration Plan is adjusted, as appropriate. B: Subsequent Iteration Plan is created prior to the iteration beginning. E: During each iteration, the current Iteration Plan is adjusted. Oracle 1Z0-466 Exam * There are two plans active in the project at any given time ?the implementation plan and the

Project Execution and Control

Question

Which three statements are true about the various plans used In OUM during Project Execution Control.

Options

  • AOnce created, the implementation Plan is never updated.
  • BThe subsequent Iteration Plan is created prior to the beginning of the next iteration.
  • CThe Project Management Plan should be updated, as appropriate.
  • DThe subsequent Iteration Plan is created as soon as possible after the Iteration begins.
  • EThe current Iteration Plan is adjusted, as appropriate.

How the community answered

(26 responses)
  • A
    12% (3)
  • B
    81% (21)
  • D
    8% (2)

Explanation

B: Subsequent Iteration Plan is created prior to the iteration beginning. E: During each iteration, the current Iteration Plan is adjusted. Oracle 1Z0-466 Exam * There are two plans active in the project at any given time ?the implementation plan and the

Topics

#Iteration Plan#Project Management Plan#execution control#plan updates