nerdexam
Oracle

1Z0-466 · Question #60

What is not a step within the Infrastructure Close task?

The correct answer is C. Conduct training of client IT staff. See the full explanation below for the reasoning.

Question

What is not a step within the Infrastructure Close task?

Options

  • AConduct a final system back-up.
  • BRevoke consultant access to client systems.
  • CConduct training of client IT staff.
  • DDocument the technical environment.

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    79% (42)
  • D
    11% (6)

Community Discussion

No community discussion yet for this question.

Full 1Z0-466 Practice