1Z0-466 · Question #59
Select the three key project roles as prescribed by OUM Manage.
The correct answer is A. Stakeholder B. Change Control Board D. Project Team. A: Project managers use OUM to make sure they and their stakeholders develop a shared understanding of what is needed, choose an appropriate architecture, and transfer the ownership of the end-product to the stakeholders. B: CCB (Change Control Board) is a review committee that…
Question
Select the three key project roles as prescribed by OUM Manage.
Options
- AStakeholder
- BChange Control Board
- CIssue Review Board
- DProject Team
- ETesting Committee
How the community answered
(61 responses)- A75% (46)
- C16% (10)
- E8% (5)
Explanation
A: Project managers use OUM to make sure they and their stakeholders develop a shared understanding of what is needed, choose an appropriate architecture, and transfer the ownership of the end-product to the stakeholders. B: CCB (Change Control Board) is a review committee that discusses and approves requests for changes to On Demand customer system configurations. The change requests are fulfilled in the A work guideline is generated by engineering for operations to use and implement. The changes are included in Oracle Certified Configurations. D: Project teams to take advantage of this experience by leveraging these leading practices along with industry standards.