In OUM Manage, what is true about Organizational Change Management process?
The correct answer is C. It feeds the communication process and risk management process and should be considered when. Organizational Change Management This process starts at the strategic level and then identifies challenges of the implementations in order to design the systems that allow lowering the risk. Identifying the change requirements from the beginning of the project would help…
Project Execution and Control
Question
In OUM Manage, what is true about Organizational Change Management process?
Options
- AIt is only a concern of a client.
- BIt feeds the risk management process and communication process and is only handled by third parties.
- CIt feeds the communication process and risk management process and should be considered when
- DIt is handled by third parties.
How the community answered
(31 responses)- A3% (1)
- B16% (5)
- C71% (22)
- D10% (3)
Explanation
- Organizational Change Management This process starts at the strategic level and then identifies challenges of the implementations in order to design the systems that allow lowering the risk. Identifying the change requirements from the beginning of the project would help organization to manage it effectively. * The Manage focus area is organized into 13 processes including the Organizational Change Management process: Oracle 1Z0-466 Exam The objective of the Organizational Change Management process is to be aware of the Client's Organizational Change Management Strategy and to effectively create a Change and Communication Plan that addresses this strategy. The goal is to create the change momentum needed to increase buy-in and reduce resistance - thus reducing productivity losses.
Topics
#Organizational Change Management#risk management#communication process#OUM Manage