1Z0-466 · Question #62
Which two statement are true about the Change Control Board (CCB)?
The correct answer is B. It is an internal project organization that is responsible for reviewing and resolving change requests. D. It escalates changes affecting scope to the steering committee. B: CCB is a review committee that discusses and approves requests for changes to On Demand customer system configurations. The change requests are fulfilled in the following ways: A work guideline is generated by engineering for operations to use and implement. The changes are…
Question
Which two statement are true about the Change Control Board (CCB)?
Options
- AIt meets daily during Project Execution and Control.
- BIt is an internal project organization that is responsible for reviewing and resolving change requests.
- CIt is a person, group, or business that has a shared interest in a particular set of activities
- DIt escalates changes affecting scope to the steering committee.
How the community answered
(25 responses)- A12% (3)
- B80% (20)
- C8% (2)
Explanation
B: CCB is a review committee that discusses and approves requests for changes to On Demand customer system configurations. The change requests are fulfilled in the following ways: A work guideline is generated by engineering for operations to use and implement. The changes are included in Oracle Certified Configurations. D: A Steering Committee is a group of high-level stakeholders who are responsible for providing guidance on overall strategic direction. They do not take the place of a Sponsor, but help to spread the strategic input and buy-in to a larger portion of the organization. The Steering Committee is usually made up of organizational peers and is a combination of direct clients and indirect stakeholders. Some members on the Steering Committee may also sit on the Change
Topics
Community Discussion
No community discussion yet for this question.