1Z0-466 · Question #51
What work product, created by the Project Manager and the client, details the approach to the project at a high level?
The correct answer is E. Project Management WBS. Activities allow the project manager to streamline creation and management of the Work Breakdown Structure (WBS) for an engagement. * Project managers use OUM to make sure they and their stakeholders develop a shared understanding of what is needed, choose an appropriate…
Question
What work product, created by the Project Manager and the client, details the approach to the project at a high level?
Options
- AProject Management Framework
- BProject Implementation Framework
- CProject Resource Framework
- DProject Work Framework
- EProject Management WBS
How the community answered
(57 responses)- A4% (2)
- B9% (5)
- C16% (9)
- D2% (1)
- E70% (40)
Explanation
Activities allow the project manager to streamline creation and management of the Work Breakdown Structure (WBS) for an engagement. * Project managers use OUM to make sure they and their stakeholders develop a shared understanding of what is needed, choose an appropriate architecture, and transfer the ownership of the end-product to the stakeholders.