nerdexam
Oracle

1Z0-466 · Question #52

What is not true about risk management in OUM Manage?

The correct answer is D. If a baseline risk assessment is done during the Project Startup phase, there are no further risk. See the full explanation below for the reasoning.

Question

What is not true about risk management in OUM Manage?

Options

  • AThe project manager should regularly conduct risk assessments.
  • BRisks become even more critical during the Project Execution and Control Phase.
  • CParticular attention should be paid to risks prior to production cutover.
  • DIf a baseline risk assessment is done during the Project Startup phase, there are no further risk

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    13% (4)
  • C
    3% (1)
  • D
    77% (24)

Community Discussion

No community discussion yet for this question.

Full 1Z0-466 Practice