1Z0-466 · Question #47
Identify two functions of the Project Management Plan [PMP].
The correct answer is A. defines the overall project management strategies and approaches C. Is the single most important work product produced by the Project Manager. The project manager creates the project management plan following input from the project team and key stakeholders. The plan should be agreed and approved by at least the project team and its key stakeholders.
Planning and Scheduling
Question
Identify two functions of the Project Management Plan [PMP].
Options
- Adefines the overall project management strategies and approaches
- BIs limited to project scope
- CIs the single most important work product produced by the Project Manager
- DIs limited to the project budget
- EIs done in project closure and is done only once
How the community answered
(25 responses)- A80% (20)
- B4% (1)
- D4% (1)
- E12% (3)
Explanation
- The project manager creates the project management plan following input from the project team and key stakeholders. The plan should be agreed and approved by at least the project team and its key stakeholders.
Topics
#Project Management Plan#PMP functions#work products#project manager role