1Z0-466 · Question #48
What is true about Organization Change Management in OUM manage?
The correct answer is D. Having nobody to manage change should be a warning sign that the project may go off track. See the full explanation below for the reasoning.
Question
What is true about Organization Change Management in OUM manage?
Options
- AA previous project failure is not a change management warning sign since it could be due to any
- BNo official communication regarding the change is issued because the client is seeking to have a
- CHave a consensus culture is good because it cuts down on the time to get to agreements.
- DHaving nobody to manage change should be a warning sign that the project may go off track.
How the community answered
(62 responses)- A5% (3)
- B10% (6)
- C2% (1)
- D84% (52)