1Z0-466 · Question #48

What is true about Organization Change Management in OUM manage?

The correct answer is D. Having nobody to manage change should be a warning sign that the project may go off track. See the full explanation below for the reasoning.

Question

What is true about Organization Change Management in OUM manage?

Options

  • AA previous project failure is not a change management warning sign since it could be due to any
  • BNo official communication regarding the change is issued because the client is seeking to have a
  • CHave a consensus culture is good because it cuts down on the time to get to agreements.
  • DHaving nobody to manage change should be a warning sign that the project may go off track.

How the community answered

(62 responses)
  • A
    5% (3)
  • B
    10% (6)
  • C
    2% (1)
  • D
    84% (52)