1Z0-466 · Question #35
Select the three ways OUM Manage can be scaled or made fit-for-purpose.
The correct answer is B. by adding more iterations to the workplan C. by combining tasks or executing at the activity level E. by eliminating unnecessary tasks from the workplan. B: Iterative and Incremental OUM recognizes the advantages of an iterative and incremental approach to development and deployment of information systems. Any of the tasks within OUM may be iterated. Whether or not to iterate, as well as the number of iterations, varies. Tasks…
Question
Select the three ways OUM Manage can be scaled or made fit-for-purpose.
Options
- Aby considering the depth to which specific tasks and activities are executed
- Bby adding more iterations to the workplan
- Cby combining tasks or executing at the activity level
- Dby including additional tasks to the workplan
- Eby eliminating unnecessary tasks from the workplan
How the community answered
(22 responses)- A14% (3)
- B82% (18)
- D5% (1)
Explanation
B: Iterative and Incremental OUM recognizes the advantages of an iterative and incremental approach to development and deployment of information systems. Any of the tasks within OUM may be iterated. Whether or not to iterate, as well as the number of iterations, varies. Tasks may be iterated to increase quality of the work products to a desired level, to add sufficient level of detail, or to refine and expand the work products on the basis of user feedback C: you should consider whether it is advisable or appropriate to combine tasks or to execute your project using OUM's activities ?which are groupings of tasks. Our next step is to eliminate activities/tasks that are not needed. Consider the following: 1. Don't eliminate anything in the Core Workflow without carefully consideration. 2. Review any available supplemental guidance. 3. Consider removing activities/tasks NOT included in the Estimate and/or Proposal. 4. Determine if it's possible to eliminate all if not most of some processes. For example, consider removing the following processes and corresponding activities and/or tasks, if your project does not include ANY requirements for them: - Performance Management - Organizational Change Management - Data Acquisition and Conversion