1Z0-466 · Question #34
According to the recommended training for this exam, what is the "triple constraint"?
The correct answer is A. time, resources, quality/scope. Scope, Time & Cost together are termed as the Triple Constraints of a Project. Risk avoidance involves changing the project plan to eliminate the risk or to protect the project objectives (time, cost, scope, quality) from its impact. The team might achieve this by changing…
Primavera P6 EPPM Introduction
Question
According to the recommended training for this exam, what is the "triple constraint"?
Options
- Atime, resources, quality/scope
- Btime, quality/scope, performance
- Cclient availability, budget, modifications
- Dproducts licensed, service requests limits, annual maintenance
How the community answered
(54 responses)- A72% (39)
- B9% (5)
- C15% (8)
- D4% (2)
Explanation
- Scope, Time & Cost together are termed as the Triple Constraints of a Project. * Risk avoidance involves changing the project plan to eliminate the risk or to protect the project objectives (time, cost, scope, quality) from its impact. The team might achieve this by changing scope, adding time, or adding resources (thus relaxing the so-called "triple constraint") Note:
Topics
#triple constraint#time cost scope#project management fundamentals#OUM framework