1Z0-466 · Question #25
Which statements are true about the active plans a project? Oracle 1Z0-466 Exam
The correct answer is A. There are two iteration plans ?one for the current iteration and a draft for the upcoming iteration. B. A subsequent iteration plan is created prior to the iteration beginning. AB (not C): During each iteration, the current Iteration Plan is adjusted. Subsequent Iteration Plan is created prior to the iteration beginning. * there are two plans active in the project at any given time ?the implementation plan and the
Question
Which statements are true about the active plans a project? Oracle 1Z0-466 Exam
Options
- AThere are two iteration plans ?one for the current iteration and a draft for the upcoming iteration.
- BA subsequent iteration plan is created prior to the iteration beginning.
- CThe iteration plan for each iteration is set and cannot be altered.
- DThe project Management Plan is a document and is not affected by the implementation Plan.
How the community answered
(24 responses)- A83% (20)
- C4% (1)
- D13% (3)
Explanation
AB (not C): During each iteration, the current Iteration Plan is adjusted. Subsequent Iteration Plan is created prior to the iteration beginning. * there are two plans active in the project at any given time ?the implementation plan and the
Topics