1Z0-466 · Question #26
Earned value is a technique to report project status using which three variables?
The correct answer is A. EV ?Earned Value B. PV ?Planned Value C. AC ?Actual Cost. EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid
Reporting and Analytics
Question
Earned value is a technique to report project status using which three variables?
Options
- AEV ?Earned Value
- BPV ?Planned Value
- CAC ?Actual Cost
- DPC ?Planned Cost
- EEC ?Earned Cost
How the community answered
(34 responses)- A79% (27)
- D12% (4)
- E9% (3)
Explanation
EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid
Topics
#earned value#planned value#actual cost#project status reporting