nerdexam
Oracle

1Z0-466 · Question #26

Earned value is a technique to report project status using which three variables?

The correct answer is A. EV ?Earned Value B. PV ?Planned Value C. AC ?Actual Cost. EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid

Reporting and Analytics

Question

Earned value is a technique to report project status using which three variables?

Options

  • AEV ?Earned Value
  • BPV ?Planned Value
  • CAC ?Actual Cost
  • DPC ?Planned Cost
  • EEC ?Earned Cost

How the community answered

(34 responses)
  • A
    79% (27)
  • D
    12% (4)
  • E
    9% (3)

Explanation

EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid

Topics

#earned value#planned value#actual cost#project status reporting

Community Discussion

No community discussion yet for this question.

Full 1Z0-466 Practice