1Z0-466 · Question #11

Which three variables are used with Earned Value?

The correct answer is A. EV - Earned Value B. PV - Planned Value C. AC - Actual Cost. EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid

Reporting and Analytics

Question

Which three variables are used with Earned Value?

Options

  • AEV - Earned Value
  • BPV - Planned Value
  • CAC - Actual Cost
  • DPC - Planned Cost
  • EEC - Earned Cost
  • FAC - Accounting Cost

How the community answered

(32 responses)
  • A
    72% (23)
  • D
    3% (1)
  • E
    16% (5)
  • F
    9% (3)

Explanation

EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid

Topics

#earned value#planned value#actual cost#EV variables