Oracle
1Z0-466 · Question #11
Which three variables are used with Earned Value?
The correct answer is A. EV - Earned Value B. PV - Planned Value C. AC - Actual Cost. EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid
Reporting and Analytics
Question
Which three variables are used with Earned Value?
Options
- AEV - Earned Value
- BPV - Planned Value
- CAC - Actual Cost
- DPC - Planned Cost
- EEC - Earned Cost
- FAC - Accounting Cost
How the community answered
(32 responses)- A72% (23)
- D3% (1)
- E16% (5)
- F9% (3)
Explanation
EV - earned value, estimated value of work done. PV - planned value, estimated value of planned work AC - actual cost, what you paid
Topics
#earned value#planned value#actual cost#EV variables
Community Discussion