nerdexam
Oracle

1Z0-466 · Question #16

What describes the initial Iteration Plan for the Inception phase?

The correct answer is B. It is created in the Project Startup Phase. The overriding goal of the Inception phase is to gain concurrence among all stakeholders on the lifecycle objectives for the project. The Inception phase is critical for all projects because the scope of the effort, the high-level requirements, and the significant risks must be…

Planning and Scheduling

Question

What describes the initial Iteration Plan for the Inception phase?

Options

  • AIt is a static plan, which is set during Bid Transition.
  • BIt is created in the Project Startup Phase.
  • CIt focuses on the milestones for the Elaboration Phase.
  • DIt is not needed because Inception is a short phase.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    85% (22)
  • C
    8% (2)
  • D
    4% (1)

Explanation

The overriding goal of the Inception phase is to gain concurrence among all stakeholders on the lifecycle objectives for the project. The Inception phase is critical for all projects because the scope of the effort, the high-level requirements, and the significant risks must be understood before the project can proceed. The Inception phase is used to kick off a project; review the strategic direction of the business; and confirm, document, and prioritize the high-level business requirements for the project. It is also the time to begin assembling and integrating the project team, to scope the entire engagement, and develop the initial project plan.

Topics

#iteration plan#inception phase#project startup#OUM phases

Community Discussion

No community discussion yet for this question.

Full 1Z0-466 Practice