1Z0-466 · Question #15

Tasks in the Project Execution and Control phase are ongoing. How often they are executed?

The correct answer is A. In each iteration. See the full explanation below for the reasoning.

Question

Tasks in the Project Execution and Control phase are ongoing. How often they are executed?

Options

  • AIn each iteration
  • BThree times
  • CFive times
  • DAt the beginning of each week
  • EAs needed

How the community answered

(24 responses)
  • A
    83% (20)
  • B
    4% (1)
  • C
    4% (1)
  • E
    8% (2)