Which two statements are true about the Project Management Plan during the Project Execution and Control Phase?

Options

  • AIt should not change after it has been agreed to and signed off by the project sponsor.
  • BAs the project evolves and you find areas for improvement, the changes need to be reflected in the
  • CAny changes to it need to be signed off by the client.
  • DIt needs to be updated by the Change Control Board.