SAFE-SP · Question #36
Which three questions should each team member answer during the daily stand-up? (Choose three.) Are there any impediments that will prevent the team from meeting the Iteration goals?
The correct answer is A. How am I splitting the Solutions into Capabilities and Enablers? D. What will I do today to advance the Iteration goals? E. How I am contributing to an environment of continuous change? Heads up: The provided correct answer (A, D, E) appears to be incorrect based on SAFe and Scrum standards. The actual three questions each team member answers during a daily stand-up are: 1. What did I do yesterday to advance the Iteration goals? (C) 2. What will I do today to…
Question
Which three questions should each team member answer during the daily stand-up? (Choose three.) Are there any impediments that will prevent the team from meeting the Iteration goals?
Options
- AHow am I splitting the Solutions into Capabilities and Enablers?
- BHow am I optimizing the full Solution?
- CWhat did I do yesterday to advance the Iteration goals?
- DWhat will I do today to advance the Iteration goals?
- EHow I am contributing to an environment of continuous change?
How the community answered
(43 responses)- A95% (41)
- B2% (1)
- C2% (1)
Explanation
Heads up: The provided correct answer (A, D, E) appears to be incorrect based on SAFe and Scrum standards.
The actual three questions each team member answers during a daily stand-up are:
- What did I do yesterday to advance the Iteration goals? (C)
- What will I do today to advance the Iteration goals? (D)
- Are there any impediments that will prevent the team from meeting the Iteration goals? (stated in the question stem)
So the correct choices from the lettered options should be C and D (with the impediments question either embedded in the stem or implied as the third).
Why the distractors are wrong:
- A ("splitting Solutions into Capabilities/Enablers") is a PI Planning or backlog refinement concern, not a stand-up question.
- B ("optimizing the full Solution") operates at a portfolio/program level, not a daily team sync.
- E ("contributing to continuous change") is not a standard stand-up question in any Agile framework.
Memory tip: Think "Yesterday → Today → Blockers" - the three daily stand-up questions are always about the past 24 hours, the next 24 hours, and anything in the way. If a choice sounds strategic or architectural rather than daily/tactical, it's a distractor.
I'd recommend verifying this question against your official SAFe study materials, as the listed answer key may contain an error.