Which statement is true about pair work in the Scaled Agile Framework?

The correct answer is A. It comes from pair programming in Extreme Programming (XP). Pair work in SAFe traces its roots directly to pair programming in Extreme Programming (XP), one of the Agile practices SAFe incorporates - making A correct. Option B is wrong because SAFe recommends pair work as a collaborative technique but imposes no specific time percentage…

Team and Technical Agility

Question

Which statement is true about pair work in the Scaled Agile Framework?

Options

  • AIt comes from pair programming in Extreme Programming (XP)
  • BIt is a best practice that team members should spend 50% to 100% of the time in pair work
  • CIt occurs during Iteration Planning
  • DIt is for developers only

How the community answered

(20 responses)
  • A
    90% (18)
  • B
    5% (1)
  • D
    5% (1)

Explanation

Pair work in SAFe traces its roots directly to pair programming in Extreme Programming (XP), one of the Agile practices SAFe incorporates - making A correct. Option B is wrong because SAFe recommends pair work as a collaborative technique but imposes no specific time percentage mandate like "50% to 100%." Option C is incorrect because pair work is not an activity tied to Iteration Planning specifically; it happens during development (Iteration Execution) when team members collaborate on tasks. Option D is wrong because pair work extends beyond developers - testers, designers, and other team members can and do pair together.

Memory tip: Think "XP DNA in SAFe" - SAFe is built on foundational Agile practices, and pair work is one of several concepts it inherited directly from XP (along with TDD, CI, etc.).