SAFE-SP · Question #28

Which statement reflects one of the steps for setting initial velocity?

The correct answer is B. The team members assess their availability, acknowledging time off and other potential v u duties. Option B is correct because setting initial velocity begins with each team member honestly assessing how much time they can actually contribute during the iteration - factoring in vacations, meetings, training, and other obligations. This capacity assessment is the foundation…

Team and Technical Agility

Question

Which statement reflects one of the steps for setting initial velocity?

Options

  • AMaintenance tasks do not need to be included in velocity; maintenance tasks fall outside thi scope
  • BThe team members assess their availability, acknowledging time off and other potential v u duties
  • CDetermining velocity is a new function in each Iteration; previous Iterations should not be ^
  • DIdentify work on technical infrastructure, tooling, and other systemic impediments

How the community answered

(18 responses)
  • B
    94% (17)
  • D
    6% (1)

Explanation

Option B is correct because setting initial velocity begins with each team member honestly assessing how much time they can actually contribute during the iteration - factoring in vacations, meetings, training, and other obligations. This capacity assessment is the foundation of a realistic velocity estimate.

Why the distractors are wrong:

  • A is incorrect because maintenance work is included in velocity; it consumes real team capacity and must be accounted for.
  • C is incorrect because historical velocity data from previous iterations is valuable input - ignoring it would make initial estimates less accurate.
  • D describes identifying technical infrastructure and impediment work, which is a backlog/planning activity, not specifically a step in calculating initial velocity.

Memory tip: Think of velocity-setting as "honest headcount" - before you can know how fast the team will move, you need to know how many real hours each person actually has. "B = Bandwidth check."

Topics

#velocity#team capacity#availability#iteration planning