SAFE-SP · Question #35
What is typically included in the definition of done for the team increment?
The correct answer is B. 45 new questions addStories are accepted by the Product Owner. In SAFe (Scaled Agile Framework), the Product Owner (PO) operates at the team level and is specifically responsible for accepting stories within the team increment - making this the standard criterion in the team-level Definition of Done. Why the distractors are wrong: A is…
Question
What is typically included in the definition of done for the team increment?
Options
- AStories are accepted by Product Management
- B45 new questions addStories are accepted by the Product Owner
- CCustomer documentation is ready
- DRegression testing is done
How the community answered
(28 responses)- A4% (1)
- B93% (26)
- C4% (1)
Explanation
In SAFe (Scaled Agile Framework), the Product Owner (PO) operates at the team level and is specifically responsible for accepting stories within the team increment - making this the standard criterion in the team-level Definition of Done.
Why the distractors are wrong:
- A is incorrect because Product Management works at the program/ART level, accepting features, not stories. Confusing Product Owner with Product Management is a classic exam trap.
- C (Customer documentation ready) is typically part of a Release or Program Increment DoD, not the team increment - it's a higher-level concern.
- D (Regression testing done) also belongs to the System Team or Program level DoD, where integration and regression testing across teams occurs, not within a single team increment.
Memory tip: Think of it as ownership matching scope - the Product Owner owns team-level stories (PO → Team → Stories), while Product Management owns program-level features. If the question mentions "stories accepted," the answer involves the Product Owner, not Product Management.