SAFE-RTE · Question #21
What are two common PI Planning anti-patterns? (Choose two.)
The correct answer is C. Too much time is spent analyzing each Story D. Scrum Masters who work with multiple teams do not have time for their teams. See the full explanation below for the reasoning.
Question
What are two common PI Planning anti-patterns? (Choose two.)
Options
- AStories are created for the Iterations
- BThe team decides which changes need to happen and when
- CToo much time is spent analyzing each Story
- DScrum Masters who work with multiple teams do not have time for their teams
- EToo much time is spent prioritizing Features
How the community answered
(25 responses)- A8% (2)
- B4% (1)
- C84% (21)
- E4% (1)