SAFE-RTE · Question #20

During Pl Planning, who owns Feature priorities?

The correct answer is C. Product Management. See the full explanation below for the reasoning.

Question

During Pl Planning, who owns Feature priorities?

Options

  • ARelease Train Engineer
  • BSolution Architect/Engineer
  • CProduct Management
  • DBusiness Owner

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    74% (26)
  • D
    14% (5)

Community Discussion

No community discussion yet for this question.