SAFE-RTE · Question #136
Product Management is responsible for which activity?
The correct answer is B. Defining Program Backlog content. See the full explanation below for the reasoning.
Question
Product Management is responsible for which activity?
Options
- AEstablishing an architectural vision for the Agile Release Release Train
- BDefining Program Backlog content
- CPrioritizing the Portfolio Backlog
How the community answered
(56 responses)- A5% (3)
- B80% (45)
- C14% (8)