When does the Plan-Do-Check-Adjust cycle occur in scrum?
The correct answer is D. A cross all scrum events. See the full explanation below for the reasoning.
Question
When does the Plan-Do-Check-Adjust cycle occur in scrum?
Options
- AAs part of the lteration retrospective
- BIn the daily stand-up
- CAt the lteration review
- DA cross all scrum events
How the community answered
(54 responses)- A4% (2)
- B15% (8)
- C6% (3)
- D76% (41)