Scaled_Agile
SAFE-RTE · Question #128
While facilitating Program Increment (PI) Planning readiness activities, the Release Train Engineer (RTE) notices a Feature that is risky to the teams because the technology is new. Which of the…
The correct answer is B. Coach the teams to create exploration Enablers. See the full explanation below for the reasoning.
Question
While facilitating Program Increment (PI) Planning readiness activities, the Release Train Engineer (RTE) notices a Feature that is risky to the teams because the technology is new. Which of the following could reduce the risk?
Options
- AEnsure engineering managers are directing the development process
- BCoach the teams to create exploration Enablers
- CAsk for a presentation of a detailed design before the PI Planning meeting
- DMake sure all the technical specifications are written before PI execution
How the community answered
(48 responses)- A4% (2)
- B85% (41)
- C8% (4)
- D2% (1)
Community Discussion
No community discussion yet for this question.