SAFE-RTE · Question #127

After an Agile Release Train's first Program Increment (PI) Planning event, what action can the Release Train Engineer take to help optimize the Program Backlog readiness for the next PI?

The correct answer is C. Coach Product Management and the System Architect to include Program Backlog refinement into. See the full explanation below for the reasoning.

Question

After an Agile Release Train's first Program Increment (PI) Planning event, what action can the Release Train Engineer take to help optimize the Program Backlog readiness for the next PI?

Options

  • AAsk Product Management and the System Architect what the new Program Back-log looks like just
  • BCompile all the teams' objectives from PI Planning and send out a summary report
  • CCoach Product Management and the System Architect to include Program Backlog refinement into
  • DAsk the Lean Portfolio Management function to hold regular Epic review meetings so new Epics

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    15% (4)
  • C
    73% (19)
  • D
    8% (2)