SAFE-RTE · Question #118

In addition to Innovation and Planning, what else does the IP Iteration provide time for?

The correct answer is A. An estimating guard band. See the full explanation below for the reasoning.

Question

In addition to Innovation and Planning, what else does the IP Iteration provide time for?

Options

  • AAn estimating guard band
  • BAn opportunity to integrate and perform end-to-end testing
  • CBuilding in quality and compliance
  • DAdditional planned work

How the community answered

(42 responses)
  • A
    76% (32)
  • B
    7% (3)
  • C
    14% (6)
  • D
    2% (1)