Which statement is true about estimating and forecasting the Portfolio Backlog?
The correct answer is A. Feature estimates are rolled up into Epic estimates. See the full explanation below for the reasoning.
Question
Which statement is true about estimating and forecasting the Portfolio Backlog?
Options
- AFeature estimates are rolled up into Epic estimates
- BRefinement is necessary when estimating the effort needed to implement an Epic
- CWSJF is used to assign Epics to Value Streams
How the community answered
(21 responses)- A81% (17)
- B14% (3)
- C5% (1)