RCDDV15 · Question #225

A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet. What activity should…

The correct answer is B. Resource Interdependency management. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet. What activity should the program manager perform next?

Options

  • AProgram delivery management
  • BResource Interdependency management
  • CProgram performance monitoring and controlling
  • DBenefits sustainment and program transition

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    82% (23)
  • C
    4% (1)
  • D
    4% (1)

Topics

#resource interdependency#change request#component management#program delivery