A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members…

The correct answer is B. Assign the tasks on the critical path to the resources available to adhere to the project schedule. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program. As a result, the program manager must do which of the following'?

Options

  • AUtilize team members that are currently available, even though they do not have the expertise
  • BAssign the tasks on the critical path to the resources available to adhere to the project schedule
  • CDelay the start of the program until the assigned resources are available
  • DApply resource leveling considering the constraints of time, budget, and quality

How the community answered

(47 responses)
  • A
    11% (5)
  • B
    79% (37)
  • C
    6% (3)
  • D
    4% (2)

Topics

#resource leveling#critical path#resource constraints#program planning