A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members…

Sign in or unlock RCDDV15 to reveal the answer and full explanation for question #221. The question stem and answer options stay visible for context.

Program Life Cycle Management

Question

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program. As a result, the program manager must do which of the following'?

Options

  • AUtilize team members that are currently available, even though they do not have the expertise
  • BAssign the tasks on the critical path to the resources available to adhere to the project schedule
  • CDelay the start of the program until the assigned resources are available
  • DApply resource leveling considering the constraints of time, budget, and quality

Unlock RCDDV15 to see the answer

You've previewed enough free RCDDV15 questions. Unlock RCDDV15 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#resource leveling#critical path#resource constraints#program planning
Full RCDDV15 Practice