A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to…

The correct answer is D. Program manager. See the full explanation below for the reasoning.

Program Stakeholder Engagement

Question

A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?

Options

  • AProgram sponsor
  • BCommunications manager
  • CProject manager
  • DProgram manager

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    18% (5)
  • C
    7% (2)
  • D
    71% (20)

Topics