The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

The correct answer is B. Gather all the details, analyze impacts, determine corrective actions and present the findings to. Option B is correct because the program manager's primary responsibility when a red flag arises is to personally own the analysis process - gather the details, assess impacts, and determine corrective actions - before escalating to sponsors or stakeholders. Presenting findings…

Program Management

Question

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

Options

  • AContact the project sponsors to present the details, impacts, and possible corrective actions
  • BGather all the details, analyze impacts, determine corrective actions and present the findings to
  • CWork with program sponsor to compile impact analysis data to obtain additional funding for the
  • DAsk the program team to compile all details, analyze impacts, determine corrective actions and

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    74% (28)
  • C
    5% (2)
  • D
    16% (6)

Explanation

Option B is correct because the program manager's primary responsibility when a red flag arises is to personally own the analysis process - gather the details, assess impacts, and determine corrective actions - before escalating to sponsors or stakeholders. Presenting findings without first doing the groundwork would be premature and undermine the program manager's credibility.

Why the distractors fail:

  • A skips the analysis phase entirely - going straight to sponsors without understanding the full picture is reactive and unprepared.
  • C prematurely assumes the solution is more funding, and leans on the sponsor to do analytical work that is the program manager's job.
  • D delegates the analytical work to the program team, which abdication of the program manager's core accountability - though the team may assist, the PM must lead and own the findings.

Memory tip: Think of it as "Gather → Analyze → Present" - the program manager always does the homework first. Whenever you see a choice that skips straight to presenting or escalating, or one that hands off responsibility to sponsors or team members, it's likely wrong.

Topics

#Cost Variance#Corrective Actions#Program Management#Stakeholder Communication