A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was…

The correct answer is C. Analyze the impact of the delay, review risks, identify any corrective actions, and update the. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved. What should the program manager do to ensure benefits realization?

Options

  • AConduct a program performance analysis based upon the deviation, and update the program
  • BInform the program sponsor and the steering committee of the delay, and validate the program
  • CAnalyze the impact of the delay, review risks, identify any corrective actions, and update the
  • DUpdate the program schedule, and escalate the issue to the program management office (PMO)

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    15% (4)
  • C
    74% (20)
  • D
    4% (1)

Topics

#performance monitoring#corrective actions#schedule variance#risk management