BICSI
RCDDV15 · Question #142
The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables…
The correct answer is B. Review the program resource management plan with the three project managers emphasizing. See the full explanation below for the reasoning.
Program Life Cycle Management
Question
The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C. Which of the following should the program manager do first?
Options
- ADirect the three project managers to crash their projects to allow project A the two months of
- BReview the program resource management plan with the three project managers emphasizing
- CConvene the change board to evaluate the cost benefit of the compression and the impact on the
- DEngage the executive sponsor and program board to evaluate the CEO's request and determine if
How the community answered
(28 responses)- A18% (5)
- B71% (20)
- C7% (2)
- D4% (1)
Topics
#schedule compression#resource management plan#program integration#stakeholder communication
Community Discussion
No community discussion yet for this question.