RCDD-002 · Question #47
Communicating a project's design and technical specifications to the client and stakeholders is part of the ___________of the project.
The correct answer is A. scope of work. Scope of work (A) is correct because it defines everything a project encompasses - including communicating the design and technical specifications to clients and stakeholders. The scope of work documents what will be delivered, how it will be built, and what standards apply…
Question
Communicating a project's design and technical specifications to the client and stakeholders is part of the ___________of the project.
Options
- Ascope of work
- Bneeds analysis
- Cclose out procedure
- Dbidding phase
How the community answered
(59 responses)- A80% (47)
- B7% (4)
- C3% (2)
- D10% (6)
Explanation
Scope of work (A) is correct because it defines everything a project encompasses - including communicating the design and technical specifications to clients and stakeholders. The scope of work documents what will be delivered, how it will be built, and what standards apply, making it the natural vehicle for sharing technical details with all parties.
Needs analysis (B) happens before design begins - it's about identifying what the client requires, not communicating the solution back to them. Close out procedure (D) occurs at the end of a project and covers final deliverables, sign-offs, and documentation handover - not design specifications. Bidding phase (C) is a procurement stage where contractors submit proposals to win the work; design specs may inform a bid, but communicating them to stakeholders is not the purpose of that phase.
Memory tip: Think of "scope of work" as the project's blueprint conversation - it's the formal channel where the team says, "Here's exactly what we're building and how." If it describes the solution in detail to those who matter, it belongs in the scope.
Topics
Community Discussion
No community discussion yet for this question.