RCDD-002 · Question #302

RCDD-002 Question #302: Real Exam Question with Answer & Explanation

The correct answer is D. Document the risk and create a mitigation plan. See the full explanation below for the reasoning.

Question

The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization. What should the program manager do next?

Options

  • AUpdate the program benefits management plan and risk register
  • BImplement the mitigation plan for the identified risk
  • CAdjust the program scope to avoid the risk
  • DDocument the risk and create a mitigation plan