During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects. What should the program…
The correct answer is B. Review and update the stakeholder engagement plan. See the full explanation below for the reasoning.
Question
During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects. What should the program manager do to address the situation'?
Options
- AReview and update the detailed stakeholder list
- BReview and update the stakeholder engagement plan
- CExecute the component project's communications management plan
- DUpdate the risk register.
How the community answered
(23 responses)- A4% (1)
- B74% (17)
- C4% (1)
- D17% (4)
Community Discussion