Question

During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects. What should the program manager do to address the situation'?

Options

  • AReview and update the detailed stakeholder list
  • BReview and update the stakeholder engagement plan
  • CExecute the component project's communications management plan
  • DUpdate the risk register.